Cost Overrun Watch

Where a project is running over budget, which cost lines are driving it, and what it will cost at completion โ€” with the basis of the forecast and what to check next.

Where
  1. Finance
  2. AI agents
  3. Cost Overrun Watch
Who
  • Company Admin
  • Project Manager
  • Accountant

An overrun is a conversation, not a document, so this agent drafts nothing. It puts the variance, its drivers and the forecast in one place, and says in plain words what to look at.

๐Ÿ“ท Screenshot spot โ€” a Cost Overrun Watch result for one project: the Outlook list with Forecast cost and its basis, the Phases over budget table, and "What is driving the cost"

Save as static/img/screenshots/ai-cost-overrun.png and replace this box with ![Cost Overrun Watch](/img/screenshots/ai-cost-overrun.png)

What it readsโ€‹

  • The project's financials โ€” contract value, budget cost, actual cost, committed cost, certified progress, forecast and margin.
  • Budget against actual by phase.
  • Committed and actual cost by cost head.
  • The actual-cost lines in the cost ledger, and the phase names.

All of it as you see it on the project's Costs and Financials tabs.

What you getโ€‹

For one project:

  • Outlook โ€” Contract value, Budget cost, Actual cost, Committed (ordered, not yet cost), Certified progress, Forecast cost (reported) with its basis, Forecast if the rest goes to budget, Forecast if current performance continues, Forecast margin, Budget spent.
  • Phases over budget โ€” Phase, Budget, Actual, Over by, Over %.
  • Cost by head โ€” Cost head, Committed, Actual, Share of actual %. The budget is not split by cost head, so this shows where the money went, not a variance.
  • What is driving the cost โ€” ledger lines grouped by phase, cost head and item, over-budget phases first, top 8.
  • Why and What to check.

The forecast is two numbers and a basis

BasisUsed whenMeaning
NOT_STARTEDNothing certified yetSpend so far plus the full budget
REMAINING_AT_BUDGETCertified progress under 10%Too early to extrapolate: actual plus the budget for the work still to do
CURRENT_PERFORMANCE10% or more certifiedActual รท progress โ€” the rest of the job goes the way it has so far

Once anything is certified, both forecasts are shown side by side, so you can say "โ‚นX if the rest goes to plan, โ‚นY if it goes like the job so far".

Alerts

AlertSeverity
Forecast cost is above the contract valueCritical
Forecast to finish over budget by 5% or moreHigh (under 5%: medium)
Actual plus committed cost already exceeds the budgetHigh
Budget is being spent 15 points or more faster than work is certifiedMedium
A phase 10% or more over its budgetHigh (under 10%: medium)
Spend on a phase with no budgetMedium

Run itโ€‹

  1. In the sidebar, open Workspaces โ€บ Finance and click Cost Overrun Watch under AI agents (or find it in AI โ€บ AI Agents).
  2. Choose the Project.
  3. Click Run agent.
  4. Read the headline and the forecast basis first, then Phases over budget and What is driving the cost.

Run it every weekโ€‹

It can run itself every Monday at 07:00 โ€” off until your Company Admin switches it on in its Schedule & delivery panel. Each Company Admin and Project Manager then gets a run covering every active project they can read, side by side in a Projects table (Project, Budget, Actual, Progress %, Forecast, Basis, Forecast vs budget, Phases over), with detail for the three worst.

Safeguardsโ€‹

  • It creates nothing.
  • You need to see project cost to run it. A Site Engineer or QS / Estimator does not see it in the hub and cannot run it.
  • A project whose financials you cannot open is left out, never estimated.
  • Every figure is the one the Financials tab computes; the AI explains them and is never asked for a number.
Read the basis before you quote the forecast

Early in a job the reported forecast assumes the rest goes to budget, which can hide a trend. Quote the two forecasts together, with the basis, or someone will quote one out of context.

Tipsโ€‹

  • Post costs to the right phase. Spend with no phase shows as "(no phase)" and cannot be compared with a budget.
  • Certify progress regularly โ€” the forecast after 10% depends on it.
  • An exposure alert (actual plus committed over budget) is your chance to stop before the next order.