Cost ledger

See what a project has committed and actually spent, by cost head, with every entry traced back to the order, issue, muster, log or bill that posted it.

Where
  1. Projects
  2. open a project
  3. Budget
  4. View cost ledger
Who
  • Company Admin
  • Project Manager
  • Accountant

Nobody types into the cost ledger. Every entry is posted by the document that caused the cost, at the moment it happens — a purchase order issued, material issued to site, a muster approved. The ledger is the one place project cost is counted, and every cost figure elsewhere in the app is read from it.

Cost ledger

Open the cost ledger​

  1. Open the project and go to the Budget tab.
  2. Click View cost ledger → at the top right.
  3. To go back, click Back to budget.

Committed and actual​

FigureWhat it means
CommittedMoney promised but not yet used — ordered, not yet received.
ActualMoney the job has used.
Committed + actualEverything already spoken for. Turns red, marked "over the revised budget", once it passes the revised budget.
Revised budgetThe budget cost, including the cost of approved variations.
Revised contractThe contract value, including approved variations.

The By cost head table splits committed and actual across the six heads: material, labour, equipment, subcontract, overhead and other expense. The head comes from the resource — cement is material, a hired pump is equipment. A service-type resource lands under other expense.

What posts cost​

When this happensCommittedActualSource shown
A purchase order is issued+ order value, line by line, before GST—PurchaseOrder
A purchase order is cancelled− the undelivered balance—PurchaseOrder
Goods are received into a store− value received, at the order ratenothing yetGoodsReceipt
A direct-charge material is received (ready-mix concrete poured off the lorry)− value received+ value receivedGoodsReceipt
Material is issued to site, or written off as wastage, damage, loss or scrap—+ issue valueStockMovement
Material is returned to the store—− return valueStockMovement
A day's muster is approved—+ wages, per phase and trade, under labourAttendance
A day's equipment log is saved—+ chargeable hours and fuel, under equipmentEquipmentLog
A subcontract is awarded+ subcontract value—SubcontractOrder
A subcontract bill is certified− certified amount+ certified amountSubcontractBill
A subcontract is closed or terminated− whatever is still uncommitted—SubcontractOrder

Transfers between stores post nothing — the company still owns the material. Plant supplied by a subcontractor posts nothing either; its cost is in their bill.

Why material is cost at issue, not at receipt

Material in the store is still stock: you can transfer it to another job or return it. It becomes this project's cost when it is issued to site. Charging it at receipt would bill the job for cement it may never use, and the cost would follow the cement around every time stock moved between projects.

Why committed cost leaves out GST

Input GST on a purchase is claimed back as input tax credit, so it is not a cost of the project. Counting it would overstate committed cost by 18–28% on every order.

Overhead has no source yet: nothing in the app posts to that head, and there is no screen for entering a one-off expense directly.

Nothing is counted twice​

Each entry is tied to the document and line that posted it. If a save is retried — a dropped connection, a second tap on the button — the retry finds the entry already there and adds nothing.

Corrections are never edits. A cancelled order, a reopened muster or a corrected equipment log posts a reversal: an entry of the opposite sign, shown in red. When the day is approved again, it posts fresh. You can always see what was charged, what was taken back, and why.

Receiving goods relieves the commitment at the purchase order's rate, so when an order is fully received its committed cost comes back to exactly zero.

Filter the entries​

  1. Click a row in By cost head to show only that head's entries. Click it again to clear.
  2. Use All heads and All entry types (committed, committed reversal, actual, actual reversal) to narrow the list.
  3. Set From and To to limit the dates.
  4. Read Total of rows shown at the foot of the list.

The entries list shows Date, Head, Type, Source, Description, Qty and Amount. The date is the day the cost belongs to — the receipt date, the issue date, the muster day — not the day somebody entered it.

The newest entries load first. The date filter works on what is loaded, so click Load older entries before filtering further back.

Who can see it​

The Company Admin, and Project Managers and Accountants on the project's team. A QS / Estimator does not see the cost ledger: rate plus cost plus contract value is margin, and the person pricing the work is kept apart from it. The Sees financials tick on the Team tab does not open the ledger.

AI

Cost Overrun Watch reads this ledger against the budget and tells you where a project is running over and which lines are driving it. It creates nothing.