Bills of quantities

Build a BOQ section by section, price its lines from rate analyses or by hand, add overhead and profit, and approve it so its rates are fixed.

Where
  1. Estimation
  2. Bills of quantities
  3. open a BOQ
Who
  • Company Admin
  • Project Manager
  • QS / Estimator

The BOQ is the priced list of work. Before the award it is your bid; after the award, the same document is the contract BOQ that every RA bill measures against.

BOQ builder

Three BOQs in a job's life​

BOQWhat it isWhere it comes from
Bid BOQYour priced offer, with no project yet — the list shows it as pre-awardYou build it, import it or have the BOQ Generator draft it
Contract BOQThe bid BOQ the contract was awarded on, now linked to the projectThe award links it — see Contracts
Budget BOQThe same work at your cost, with no profitDerived from the contract BOQ on the project's Budget tab

When you create a BOQ, its Kind is client, budget, subcontract or tender. Bids are normally client or tender.

Create a BOQ​

  1. Open Estimation from the sidebar and click New BOQ.
  2. Enter a Name and pick the Kind.
  3. Leave Project as — pre-award — for a bid. The award links it to the project later.
  4. Set Overhead %, Profit % and Contingency % for the whole bill, and any Notes.
  5. Click Create and open builder. The BOQ is numbered like BOQ/26-27/0001 and starts as a Draft.

To bring in the client's workbook instead, see Import a BOQ from Excel.

Add sections​

In the Sections panel, enter a Code (such as 2), a Name (such as Substructure), a Sequence and, for a sub-section, a Parent. Click Add section. A section's subtotal includes everything filed under its sub-sections. Lines can also sit at the top level with no section.

Add lines​

  1. In the Lines panel, click Add line.
  2. Enter the Item code (such as 2.1.3) and pick the Type and Section.
  3. To price from your library, pick a Rate analysis. Its description, unit and rate fill in; the rate is copied onto the line.
  4. Enter or check the Description, Unit and Quantity. Change the Rate if you need to.
  5. Add GST % if the line carries a specific rate, and tick Variation item for extra work.
  6. Click Add line. The form keeps the section and type for the next line.
TypeUse it forIn the total?
WorkAn ordinary measured itemYes
Provisional sumAn allowance for work not yet definedYes
Prime costA PC sum for a supply the client will selectYes
Day workWork paid by time and materialsYes
Rate onlyA rate quoted without a quantityNo — it carries no quantity until measured
HeadingA title row inside a sectionNo — no unit, quantity or rate

To change a line, click Edit on its row. You can change Description, Unit, Quantity, Rate, GST %, Section and Sequence, then click Save line.

How the total is built​

FigureCalculation
SubtotalSum of line amounts (quantity × rate)
OverheadSubtotal × overhead %
Profit(Subtotal + overhead) × profit %
Contingency(Subtotal + overhead + profit) × contingency %
TotalSubtotal + overhead + profit + contingency

Change the percentages and the name in the Header panel and click Save header.

Review and approve​

DraftUnder reviewApprovedSuperseded
ButtonFromWho
Submit for reviewDraftProject Manager, Company Admin
Return to draftUnder reviewProject Manager, Company Admin
ApproveDraft or Under reviewProject Manager, Company Admin
Mark supersededApproved, with a reasonProject Manager, Company Admin

The QS / Estimator builds and prices the BOQ but does not see these buttons — tell your Project Manager when it is ready.

Approving freezes a snapshot of the whole bill. Each one is listed in the Revisions panel with its date, reason, number of lines, subtotal and total.

An approved BOQ takes no new lines

Once approved, Add line disappears and there is no way back to Draft. You can still edit a line's rate or quantity, but only with a written reason. Approve when the bill is complete; after the award, new work comes in through a change order.

Quote from the BOQ​

Click New quotation from this BOQ at the top of the builder. The quotation form opens with this BOQ selected. See Quotations.

Who sees rates​

RoleSees in a BOQ
Company Admin, Project Manager, QS / Estimator, AccountantQuantities, rates, amounts and totals
Site Engineer, QA/QC Engineer, Procurement ManagerQuantities only — the rate and amount columns are not there

On a project's BOQ tab, quantity-only roles also see a note that the rates were withheld. The tab adds an Executed column — what RA bills have measured against each line — with Progress in percent, and counts Over-measured lines, where executed quantity has gone past the BOQ quantity.

Tips​

  • Lines and sections cannot be deleted, and a line's type cannot be changed after it is added. Check the type before you click Add line.
  • A BOQ that is superseded cannot be quoted from or edited.
AI

The BOQ Generator drafts a BOQ from a typed scope or a messy file, and Resource Catalog Match links lines to your resource catalogue.