Subcontracts

Let a work package to a subcontractor, award it, record and certify their running bills with retention, advance recovery and TDS, and see where you are paying ahead of the client.

Where
  1. Projects
  2. open a project
  3. Subcontract
Who
  • Company Admin
  • Project Manager
  • Procurement Manager

A subcontract (work order) lets a package of work β€” shuttering, plastering, waterproofing β€” to a subcontractor at agreed rates. It is the mirror of your own RA bill: they measure, you certify, and you hold back retention from them the way your client holds it from you.

πŸ“· Screenshot spot β€” a project's Subcontract tab with one awarded package open: the header figures (contract value, retention, advance, TDS), the Lines table and the Subcontractor bills panel with one certified bill

Save as static/img/screenshots/procurement-subcontracts.png and replace this box with ![Subcontracts](/img/screenshots/procurement-subcontracts.png)

Draft a subcontract​

Who: Project Manager, Procurement Manager, Company Admin.

  1. Open the project and go to the Subcontract tab.

  2. Click New subcontract.

  3. Choose the Subcontractor. Only vendors of kind Subcontractor are listed β€” if yours is missing, add them under Vendors first.

  4. Enter the Package title, Work category (for example "Shuttering"), Rate type (item rate, lumpsum or labour rate), Start and End.

  5. Enter the commercial terms:

    FieldWhat it does
    Retention %Held back from each bill
    Retention cap %The most you will hold in total, as a percentage of the order value
    Advance β‚ΉAny advance paid to the subcontractor
    Advance recovery %How much of each bill goes to recovering that advance
    TDS sectionDefaults to 194C
    TDS rate %Deducted from each bill. Leave it blank and no TDS is deducted
  6. Add the Scope of work.

  7. For each line, pick the Client BOQ line it corresponds to (this fills in description, unit and quantity, which you can change), or leave it on "none". The picker works only when the project has a contract BOQ. Enter Description, Unit, Quantity and Rate. Click Add line for more.

  8. Click Save as draft. The order value is the sum of the lines.

Subcontracts are numbered per project, for example PRJ-07/SC/03. Even a lumpsum package needs at least one line in the app, because the line carries its value.

A draft cannot be edited in the app yet. If it is wrong, ask the Company Admin to Terminate it and draft a new one.

Award it​

Only the Company Admin can award a subcontract. Open the draft and click Award.

Awarding commits the whole order value to the project's subcontract cost. It is refused if the order has no lines or is worth nothing.

How a subcontract moves​

DraftAwardedIn progressCompletedClosed
Awarded or In progressSuspendedIn progress
Any status before CompletedTerminatedClosed

Every move is the Company Admin's, using the buttons on the open package: Award, Start work, Suspend, Mark completed, Terminate and Close. Suspend and Terminate offer a box for the reason; it is optional, but it is kept on the record. The first certified bill moves an awarded package to In progress by itself.

The Past their end date figure at the top of the tab counts open packages whose end date has passed; each shows an overrun tag.

Record a subcontractor's bill​

Who: Project Manager, Company Admin. A bill is money throughout, so only roles that can see project cost see the bills panel.

A bill can be recorded while the package is awarded, in progress or completed β€” and only when no earlier bill is still Received or Under review.

  1. Open the package. In Subcontractor bills, click Record bill.
  2. Enter the Bill date, Period from, Period to and Their bill no.
  3. Enter any Other deductions β‚Ή and Deduction notes.
  4. For each line being billed, enter the Qty to date β€” the cumulative quantity from the start of the order, as on a client RA bill. Leave a line blank to leave it out.
  5. Click Record bill.

The app works the bill out:

FigureHow
This bill(Qty to date βˆ’ quantity certified before) Γ— rate, over all lines
RetentionThis bill Γ— retention %, until the cap is reached
Advance recoveryAt the recovery %, until the advance is recovered
TDSThis bill Γ— TDS rate %
Net payableThis bill βˆ’ retention βˆ’ advance recovery βˆ’ TDS βˆ’ other deductions

A quantity to date above the ordered quantity is refused β€” the subcontractor is billing more than they were ordered. That excess needs a subcontract variation, and subcontract variations are not in the app yet.

Certify, reject or mark paid​

Who certifies: Project Manager, Company Admin.

  1. Open the bill and click Certify….
  2. For each line, enter the Certify qty to date, or leave it blank to accept what was claimed.
  3. Enter the Certified amount β‚Ή, or leave it blank for the full claim. You cannot certify more than this bill claims.
  4. Add Certification notes and click Certify bill.

Certifying moves the certified amount from committed to actual subcontract cost on the project, and records the retention as money you owe the subcontractor, due for release on completion. It cannot be undone.

The other buttons on a bill: Take under review, Reject (a reason is required β€” the subcontractor has to know what to correct) and, on a certified bill, Mark paid. Marking a bill paid also needs the right to record payments, so in practice it is the Company Admin who does it.

ReceivedUnder reviewCertifiedPaid
Received or Under reviewRejected

Terminating releases only what is outstanding​

The rule that matters

When a subcontract is terminated or closed, only the outstanding commitment comes off the project's committed cost β€” the order value less everything certified so far. What has been certified is work done; it stays as actual cost.

Back-to-back check against the client​

For lines linked to a client BOQ line, the Back-to-back vs client BOQ panel lists every line where you have certified more to the subcontractor than the client has certified to you: Certified to sub, Certified by client, Ahead by and Exposure (the extra quantity at the subcontractor's rate).

tip

This is a warning, never a block β€” paying a subcontractor ahead of the client is sometimes necessary. But it is money out before it is earned back, so link every line you can to the client BOQ when you draft the package. Without the link there is nothing to compare.

Who sees what​

Values, rates, bills and the back-to-back panel show only to the Project Manager, Accountant and Company Admin. A Procurement Manager can draft packages and see their lines and quantities, but not the money. A team member with Financials ticked on the project's Team page also sees the package values and rates, though not the bills.

  • Vendors β€” a subcontract needs a vendor of kind Subcontractor.
  • RA bills β€” the client-side bill that subcontractor bills mirror.
  • Costs β€” where committed and actual subcontract cost show up.
  • Payments β€” paying certified bills.