A resource is anything a rate analysis consumes: a bag of cement, a mason-day, a mixer-hour, a lump of subcontracted waterproofing, a survey fee. Get the catalogue right first — rate analyses, BOQs, material requests and purchase orders all pick from it.

Resources

The five kinds​

KindExamplesHeld in stock?
MaterialCement, TMT bars, tiles, ready-mixYes — shown as stockable
LabourMason, bar bender, helperNo — shown as direct
EquipmentMixer, JCB, tower craneNo
SubcontractWaterproofing package, false ceilingNo
ServiceSurvey, testing, design feeNo

The kind decides which cost head the resource lands in, and it is fixed once the resource is created. Only materials can carry minimum and maximum stock levels.

Add a resource​

  1. Open Resources (under Masters in the sidebar) and click New resource.
  2. Enter a Code (such as CEM-OPC53) and a Name. Codes are unique.
  3. Pick the Kind and the Unit.
  4. Optionally pick a Category, and add HSN / SAC and Brand.
  5. Enter the Standard rate — the estimating rate every rate analysis and BOQ inherits — and GST %.
  6. For a material, add Min stock and Max stock if you want reorder levels.
  7. Click Save resource.

Units​

The Unit list is a standard list set up for your company: counts (nos, set, pair, bag, roll, coil, bundle), lengths (m, rmt, km, mm), areas (sqm, sqft), volumes (cum, cft, litre, brass), weights (kg, MT, quintal), time (day, hour, shift, month) and lump sums (LS, job, %). Each unit carries its GST unit code, so the BOQ can say "cum" while a GST return says what the law needs.

Adding your own unit is not in the app yet. Pick the nearest standard unit.

Rates and what each one means​

Open a resource by clicking its row. If your role can see rates, the panel shows Standard rate, Last purchase, Average and GST.

The Standard rate is the one that matters for estimating. You set it, and it is what every rate analysis and BOQ assumes the resource costs. A purchase never changes it: what the last load of cement cost is a fact, what your estimates should assume it costs is a decision.

Last purchase and Average are not filled in from goods receipts yet, so they usually show a dash. The weighted average cost of material actually in stock is kept per store — see Stores.

There is no rate-history screen in the app yet. Every standard-rate change is recorded with its reason.

Change a standard rate​

  1. Open the resource and click Edit.
  2. Change Standard rate.
  3. Fill in Reason for the rate change (required).
  4. Click Save changes.
Rate analyses go stale — they are not recalculated

Every rate analysis that uses this resource is flagged stale, with the old and new rate in the reason. Nothing is recalculated automatically, because a BOQ or quotation may already have been priced from it. Open the Estimation page to review and recompute.

Only the Company Admin, Project Manager and QS / Estimator can change a standard rate. A Procurement Manager can add and edit resources and set the standard rate when creating one, but on an existing resource the field is greyed out.

Categories​

Click Categories to group the catalogue (for example Cement, Steel, Finishes, under a parent such as Civil). Enter Code, Name and Parent (or Top level) and click Add. Use Rename or Retire on any row. A category with resources or sub-categories in it cannot be retired — move them first.

Filter the list with All kinds, All categories and Search name or code. The list shows the first 200 matches; narrow the filters to reach the rest.

Delete a resource​

Click Delete, optionally give a reason, and confirm with Delete resource. It stops being offered on new documents; rate analyses, BOQs and orders that already name it stay readable.

Materials that go straight to cost​

Every material you receive goes into stock first and becomes project cost when it is issued. Marking a material such as ready-mix concrete — poured off the lorry, never stored — so that it posts straight to cost on receipt is not in the app yet.

Who sees rates​

RoleSees
Company Admin, Project Manager, QS / Estimator, Procurement Manager, AccountantThe resource and its rates
Site Engineer, Store Keeper, QA/QC EngineerThe resource without any rate